Falmouth Middle School<!img src="/media/pdf3.png" align=left border=0> |
Description: 4.3 MMBTU/hr Messersmith/Hurst Wood Chip Boiler
Contact Information
Address
51 Woodville Road
Falmouth, ME 04105
County
Cumberland County
Operations Contact
Topper West
Director of Facilities
207-781-3200
|
Existing Site Information
Facility - Type |
Pulbic School building |
Multi phase project (Y/N) |
N |
Additional phase costs ($) |
na |
Facility - Size (Total) Sq Ft |
106,000 |
Total number of Students |
739 |
Total number of Staff (in FTE's) |
75 |
Building One |
Falmouth Middle School |
Square Feet |
106,000 |
Age |
35 |
Pipe Distance (ft) |
0 |
Building Two |
|
Square Feet |
|
Age |
|
Pipe Distance (ft) |
|
Building Three |
na |
Square Feet |
na |
Age |
na |
Pipe Distance (ft) |
na |
Building Four
|
na |
Square Feet
|
na |
Age |
na |
Pipe Distance (ft) |
na |
Current system - Type |
#2 oil |
Steam (S) or Hot Water (HW) |
HW |
Current Boiler - Name of |
Hurst Model FB 1000 5MMBTU/hr |
Current Boiler Age (In Years) |
1963 & 1980 |
Control System (Manufacturer) |
|
Current Type |
#2 oil |
Current Fuel Volume to be displaced (Gallons) |
41,030 |
Fuel Use Data (Years + Average) (Gallons) |
51,288 |
Project Information
New System Boiler - Name |
Messersmith/Hurst |
New System Boiler - Model Number |
|
New System Boiler - Rated Capacity |
4.3 MMBTU/hr |
Fuel Type (Chips Or Pellets) |
Chips |
New System Steam (s) or Hot Water (HW) |
HW |
Storage Type |
Below grade double wide |
Storage Location |
New Structure |
Storage Capacity Tons |
60 |
Storage Description Notes |
|
Fuel Primary Transport Type |
Translating Auger |
Fuel Secondary Transport Type |
Auger |
Boiler Location (Existing Space or New Space) |
New Structure |
If New Space - Building Description |
New Structure |
New Space - Size |
74' x 31.5' |
Thermal Storage (Y/N) |
N |
Thermal Storage Capacity |
na |
System Connection(s) Description |
Full integration with exising systems |
Heat Exchanger (Y/N) |
N |
Grant Amount |
$ 500,000.00 |
Owner Cost Share |
$ 1,494,500.00 |
Total Cost |
$ 1,994,500.00 |
Application Date |
March 21, 2011 |
Completion Date |
February 28, 2013 |
Estimates
Historic Oil Use (Annual Average) (gallons) |
51,288 |
Historic Oil Use (Annual Average) (cost $$$) |
$ 158,992,80 |
Historic Fuel Volume to be Displaced (Gallons) |
41,030 |
Expected Cost of Displaced Fuel - Total $$$ |
$ 127,193.00 |
Base Fuel Price 1 (Used in Application) |
$ 3.10 |
Base Fuel Price 2 (Used in Application) |
$ - |
|
|
Wood Fuel Price (Used in Application) |
$56 .00 |
Expected Wood Use - Tons |
541 |
Expected Wood Use - $$$ |
$ 30,296.00 |
|
|
Expected Annual Oil Use
(Gallons in Addition to Wood) |
10,258 |
Expected Annual Oil Cost
($$$ in Addition to Wood) |
$31,799.80 |
|
|
Total cost of Wood and Oil (Annual) - $$$ |
$ 62,095.80 |
Expected Annual Fuel Savings -$$$ |
$ 96,897.00 |
|
|
Expected Savings Shown in Application |
$ 92,878.00 |
Historical Data
Base Fuel Price 1 (Used in Application) |
$ 3.10 |
Base Fuel Price 2 (Used in Application) |
$ - |
Wood Fuel Price (Used in Application) |
$ 56.00 |
Five Year Fuel Use History Year 1 |
|
Calendar Year |
|
Fuel Use in Gallons |
|
Fuel Use Cost ($) |
$ |
|
Five Year Fuel Use History Year 2 |
|
Calendar Year |
|
Fuel Use in Gallons |
|
Fuel Use Cost ($) |
$ |
|
|
|
Five Year Fuel Use History Year 3 |
|
Calendar Year |
|
Fuel Use in Gallons |
|
Fuel Use Cost ($) |
$ |
|
Five Year Fuel Use History Year 4 |
|
Calendar Year |
|
Fuel Use in Gallons |
|
Fuel Use Cost ($) |
$ |
|
|
|
Five Year Fuel Use History Year 5 |
|
Calendar Year |
|
Fuel Use in Gallons |
|
Fuel Use Cost ($) |
$ |
|
|
Five Year Total Fuel Use (Gallons) |
|
Five Year Yearly Average Fuel Use (Gallons) |
|
Five Year Total Fuel Cost ($) |
$ |
Five Year Average Fuel Cost ($) |
$ |
Fuel Use
|
Year Ending |
4/30/2013 |
4/30/2014 |
4/30/2015 |
4/30/2016 |
4/30/2017 |
Cumulative
Totals |
|
PELLETS used |
722.12 |
|
|
|
|
722.12 |
(in tons) |
ACTUAL COST |
$44,771.44 |
|
|
|
|
$44,771.44 |
(cost + shipping costs) |
OIL used |
19,566.40 |
|
|
|
|
19,566.40 |
(in gallons) |
ACTUAL COST |
$57,525.22 |
|
|
|
|
$57,525.22 |
(delivered cost) |
TOTAL COST |
$102,296.66 |
|
|
|
|
$102,296.66 |
(cost of both fuels) |
|
Additional Notes
Categories
Cumberland County, Hot Water, Wood Chips,