Description: 7.1 MMBTU/hr Messersmith Wood Chip Boiler
Contact Information
Address
41 Heath Street
Oakland, ME 04963
County
Kennebec County
Existing Site Information
| Facility - Type |
Public School Building RSU 18 |
| Multi phase project (Y/N) |
N |
| Additional phase costs ($) |
na |
| Facility - Size (Total) Sq Ft |
336,924 |
| Total number of Students |
1,693 |
| Total number of Staff (in FTE's) |
|
| Building One |
High School |
| Square Feet |
162,719 |
| Age |
43 |
| Pipe Distance (ft) |
1,600 |
| Building Two |
Middle School |
| Square Feet |
120,224 |
| Age |
7 |
| Pipe Distance (ft) |
400 |
| Building Three |
Williams Elementary School |
| Square Feet |
53,981 |
| Age |
87 |
| Pipe Distance (ft) |
800 |
Building Four
|
na |
Square Feet
|
na |
| Age |
na |
| Pipe Distance (ft) |
na |
| Current system - Type |
#2 oil |
| Steam (S) or Hot Water (HW) |
HW |
| Current Boiler - Name of |
|
| Current Boiler Age (In Years) |
43 |
| Control System (Manufacturer) |
Honeywell |
| Current Type |
#2 oil |
| Current Fuel Volume to be displaced (Gallons) |
70,383 |
| Fuel Use Data (Years + Average) (Gallons) |
78,203 |
Project Information
| New System Boiler - Name |
Messersmith |
| New System Boiler - Model Number |
|
| New System Boiler - Rated Capacity |
7.1 MMBTU/hr |
| Fuel Type (Chips Or Pellets) |
Chips |
| New System Steam (s) or Hot Water (HW) |
HW |
| Storage Type |
Double wide below grade bin |
| Storage Location |
At bus barn and maintenance area |
| Storage Capacity Tons |
90 |
| Storage Description Notes |
Double wide below grade bin |
| Fuel Primary Transport Type |
Translating Auger |
| Fuel Secondary Transport Type |
Conveyer belt / Auger |
| Boiler Location (Existing Space or New Space) |
New building |
| If New Space - Building Description |
Stick built - metal siding and metal roof |
| New Space - Size |
24 x 103 |
| Thermal Storage (Y/N) |
N |
| Thermal Storage Capacity |
na |
| System Connection(s) Description |
Full integration with exising systems |
| Heat Exchanger (Y/N) |
N |
| Grant Amount |
$ 500,000.00 |
| Owner Cost Share |
$ 3,138,749.00 |
| Total Cost |
$ 3,638,749.00 |
| Application Date |
March 18, 2011 |
| Completion Date |
October 12, 2012 |
Estimates
| Historic Oil Use (Annual Average) (gallons) |
78,203 |
| Historic Oil Use (Annual Average) (cost $$$) |
$ 234,609.00 |
| Historic Fuel Volume to be Displaced (Gallons) |
70,383 |
| Expected Cost of Displaced Fuel - Total $$$ |
$ 211,149.00 |
| Base Fuel Price 1 (Used in Application) |
$ 3.00 |
| Base Fuel Price 2 (Used in Application) |
$ - |
| |
|
| Wood Fuel Price (Used in Application) |
$ 55 .00 |
| Expected Wood Use - Tons |
1,400 |
| Expected Wood Use - $$$ |
$ 77,000 .00 |
| |
|
Expected Annual Oil Use
(Gallons in Addition to Wood) |
7820 |
Expected Annual Oil Cost
($$$ in Addition to Wood) |
$ 23,460.00 |
| |
|
| Total cost of Wood and Oil (Annual) - $$$ |
$ 100,460.00 |
| Expected Annual Fuel Savings -$$$ |
$ 157,609.00 |
| |
|
| Expected Savings Shown in Application |
$ 92,670.00 |
Historical Data
| Base Fuel Price 1 (Used in Application) |
$ 3.00 |
| Base Fuel Price 2 (Used in Application) |
$ - |
| Wood Fuel Price (Used in Application) |
$ 55.00 |
| Five Year Fuel Use History Year 1 |
|
| Calendar Year |
2010 |
| Fuel Use in Gallons |
63,583 |
| Fuel Use Cost ($) |
$ |
|
| Five Year Fuel Use History Year 2 |
|
| Calendar Year |
2009 |
| Fuel Use in Gallons |
72,781 |
| Fuel Use Cost ($) |
$ |
|
| |
|
| Five Year Fuel Use History Year 3 |
|
| Calendar Year |
2008 |
| Fuel Use in Gallons |
76,195 |
| Fuel Use Cost ($) |
$ |
|
| Five Year Fuel Use History Year 4 |
|
| Calendar Year |
2007 |
| Fuel Use in Gallons |
72,222 |
| Fuel Use Cost ($) |
$ |
|
| |
|
| Five Year Fuel Use History Year 5 |
|
| Calendar Year |
|
| Fuel Use in Gallons |
|
| Fuel Use Cost ($) |
$ |
|
|
| Five Year Total Fuel Use (Gallons) |
284,781 |
| Five Year Yearly Average Fuel Use (Gallons) |
71,195 |
| Five Year Total Fuel Cost ($) |
$ |
| Five Year Average Fuel Cost ($) |
$ |
Fuel Use
|
|
| Year Ending |
4/30/2013 |
4/30/2014 |
4/30/2015 |
4/30/2016 |
4/30/2017 |
Cumulative
Totals |
|
| PELLETS used |
1,275.26 |
|
|
|
|
1,275.26 |
(in tons) |
| ACTUAL COST |
$70,139.30 |
|
|
|
|
$70,139.30 |
(cost + shipping costs) |
| OIL used |
8,138.00 |
|
|
|
|
8,138.00 |
(in gallons) |
| ACTUAL COST |
$26,407.00 |
|
|
|
|
$26,407.00 |
(delivered cost) |
| TOTAL COST |
$96,546.30 |
|
|
|
|
$96,546.30 |
(cost of both fuels) |
| |
Additional Notes
Categories
Hot Water, Kennebec County, Wood Chips,