Millinocket Regional Hospital<!img src="/media/pdf3.png" align=left border=0> |
Description: 2.2MMBTU/hr Schmid UTSP 700 Pellet Boiler
Contact Information
Address
200 Somerset Street
Millinocket, ME 04662
County
Penobscot County
Existing Site Information
Facility - Type |
Medical Center / Hospital |
Multi phase project (Y/N) |
N |
Additional phase costs ($) |
na |
Facility - Size (Total) Sq Ft |
70,000 |
Total number of Students |
|
Total number of Staff (in FTE's) |
|
Building One |
Millinocket Regional Medical Center |
Square Feet |
70,000 |
Age |
55 |
Pipe Distance (ft) |
0 |
Building Two |
na |
Square Feet |
na |
Age |
na |
Pipe Distance (ft) |
na |
Building Three |
na |
Square Feet |
na |
Age |
na |
Pipe Distance (ft) |
na |
Building Four
|
na |
Square Feet
|
na |
Age |
na |
Pipe Distance (ft) |
na |
Current system - Type |
#2 oil |
Steam (S) or Hot Water (HW) |
S |
Current Boiler - Name of |
HB Smith Mills |
Current Boiler Age (In Years) |
|
Control System (Manufacturer) |
Honeywell Comfortpoint |
Current Type |
#2 oil |
Current Fuel Volume to be displaced (Gallons) |
79,954 |
Fuel Use Data (Years + Average) (Gallons) |
79,954 |
Project Information
New System Boiler - Name |
Schmid |
New System Boiler - Model Number |
UTSP 700 |
New System Boiler - Rated Capacity |
2.2 MMBTU/hr |
Fuel Type (Chips Or Pellets) |
Pellets |
New System Steam (s) or Hot Water (HW) |
S |
Storage Type |
External Silo |
Storage Location |
New silo adjacent to boiler room |
Storage Capacity Tons |
38 |
Storage Description Notes |
metal silo |
Fuel Primary Transport Type |
Pneumatic |
Fuel Secondary Transport Type |
Pneumatic |
Boiler Location (Existing Space or New Space) |
New |
If New Space - Building Description |
|
New Space - Size |
na |
Thermal Storage (Y/N) |
N |
Thermal Storage Capacity |
na |
System Connection(s) Description |
Full integration with exising systems |
Heat Exchanger (Y/N) |
N |
Grant Amount |
$ 258,978.00 |
Owner Cost Share |
$ 258,977 .00 |
Total Cost |
$ 517,955.00 |
Application Date |
March 24, 2011 |
Completion Date |
January 24, 2013 |
Estimates
Historic Oil Use (Annual Average) (gallons) |
79,954 |
Historic Oil Use (Annual Average) (cost $$$) |
$ 275,841.30 |
Historic Fuel Volume to be Displaced (Gallons) |
79,954 |
Expected Cost of Displaced Fuel - Total $$$ |
$275,841.30 |
Base Fuel Price 1 (Used in Application) |
$ 3.45 |
Base Fuel Price 2 (Used in Application) |
$ - |
|
|
Wood Fuel Price (Used in Application) |
$235 .00 |
Expected Wood Use - Tons |
665 |
Expected Wood Use - $$$ |
$ 156,275.00 |
|
|
Expected Annual Oil Use
(Gallons in Addition to Wood) |
0 |
Expected Annual Oil Cost
($$$ in Addition to Wood) |
$ |
|
|
Total cost of Wood and Oil (Annual) - $$$ |
$ 156,275.00 |
Expected Annual Fuel Savings -$$$ |
$ 119,566.30 |
|
|
Expected Savings Shown in Application |
$119,000 .00 |
Historical Data
Base Fuel Price 1 (Used in Application) |
$ 3.45 |
Base Fuel Price 2 (Used in Application) |
$ - |
Wood Fuel Price (Used in Application) |
$ 235.00 |
Five Year Fuel Use History Year 1 |
|
Calendar Year |
|
Fuel Use in Gallons |
|
Fuel Use Cost ($) |
$ |
|
Five Year Fuel Use History Year 2 |
|
Calendar Year |
|
Fuel Use in Gallons |
|
Fuel Use Cost ($) |
$ |
|
|
|
Five Year Fuel Use History Year 3 |
|
Calendar Year |
|
Fuel Use in Gallons |
|
Fuel Use Cost ($) |
$ |
|
Five Year Fuel Use History Year 4 |
|
Calendar Year |
|
Fuel Use in Gallons |
|
Fuel Use Cost ($) |
$ |
|
|
|
Five Year Fuel Use History Year 5 |
|
Calendar Year |
|
Fuel Use in Gallons |
|
Fuel Use Cost ($) |
$ |
|
|
Five Year Total Fuel Use (Gallons) |
365,164 |
Five Year Yearly Average Fuel Use (Gallons) |
73,033 |
Five Year Total Fuel Cost ($) |
$ 655,507.00 |
Five Year Average Fuel Cost ($) |
$ 131,101.40 |
Fuel Use
|
Year Ending |
4/30/2013 |
4/30/2014 |
4/30/2015 |
4/30/2016 |
4/30/2017 |
Cumulative
Totals |
|
PELLETS used |
242.39 |
|
|
|
|
242.39 |
(in tons) |
ACTUAL COST |
46,538.88 |
|
|
|
|
46,538.88 |
(cost + shipping costs) |
OIL used |
18,075.00 |
|
|
|
|
18,075.00 |
(in gallons) |
ACTUAL COST |
$60,196.55 |
|
|
|
|
$60,196.55 |
(delivered cost) |
TOTAL COST |
$106,735.43 |
|
|
|
|
$106,735.43 |
(cost of both fuels) |
|
Additional Notes
Categories
Penobscot County, Steam, Wood Chips,